KazMunayGas, Eni Complete Key Phase of Hybrid Energy Complex

Source: KazMunayGas

KazMunayGas, Eni Complete Key Phase of Hybrid Energy Complex

Kazakhstan’s KazMunayGas and Italy’s Eni have completed construction of a 120 MW gas-fired power plant in Zhanaozen, Mangystau Region, as part of a 247 MW hybrid energy complex.

According to KazMunayGas, the country’s national oil and gas company, the facility began supplying electricity to the commercial grid in July 2026. Since then, it has generated more than 26 million kWh of electricity, The Caspian Post reports.

The gas-fired plant comprises a turbine hall, administrative and service buildings, storage facilities, a gas pipeline, a substation and a 110 kV transmission line. More than 3 million working hours were recorded during construction without any injuries resulting in lost working time.

The facility forms part of a hybrid energy complex combining three power generation sources: a 50 MW solar power plant, a 120 MW gas-fired facility and a 77 MW wind farm.

The solar power plant, the first component of the complex, was commissioned in September 2025 and has generated approximately 93 million kWh of electricity.

Construction of the wind farm is still underway. The main civil works are expected to be completed by the end of 2026, with the installation of the first wind turbines scheduled to begin afterward. The facility is expected to become operational in 2027.

Once all three components are operational, the complex is expected to create 77 permanent jobs and ensure a stable electricity supply to KazMunayGas subsidiaries in the region, including Ozenmunaigas and KazGPZ.

KazMunayGas Chairman Askhat Khassenov said renewable energy sources would account for approximately 35% of the complex's total electricity generation once the entire facility becomes operational.

He added that the project supports Kazakhstan's efforts to achieve carbon neutrality by 2060.